GSLV-F06 Mission Failure
| Author | Message |
|---|---|
|
Space Walker ![]()
Joined: Tue Sep 15, 2009 11:59 pm
Posts: 188 |
Vehicle has just exploded - looks like altitude=13km @ ~50secs into the flight.
|
| Back to top |
|
|
Moon Mission Member ![]()
Joined: Fri Jan 09, 2004 11:52 am
Posts: 1267 Location: Exeter, Devon, England |
Ouch!
_________________ > http://www.fullmoonclothing.com > http://www.facebook.com/robsastrophotography > robgoldsmith@hotmail.co.uk |
| Back to top |
|
|
Space Station Commander ![]()
Joined: Thu Oct 27, 2005 7:44 am
Posts: 625 Location: Haarlem, The Netherlands |
Well, in their defence, it is the time of the year for fireworks
_________________ Say, can you feel the thunder in the air? Just like the moment ’fore it hits – then it’s everywhere What is this spell we’re under, do you care? The might to rise above it is now within your sphere Machinae Supremacy – Sid Icarus |
| Back to top |
|
|
Space Station Commander ![]()
Joined: Mon Dec 18, 2006 11:15 pm
Posts: 606 Location: Columbus, GA USA |
Guess they didn't get that leak fixed after all.
Just kidding, bummer about the mission. This is going to put them back a few steps... |
| Back to top |
|
|
Space Walker ![]()
Joined: Tue Sep 15, 2009 11:59 pm
Posts: 188 |
This seems to be the sequence of events leading to failure, imho:
1) aerodynamic stresses/vibrations build up as rocket traverses Max-Q 2) stresses/vibrations snap control cables 3) loss of control cable connectivity means engines stop responding to guidance correction commands 4) rocket loses correct orientation and angle of attack relative to slipstream, causing buildup of shear forces 5) rocket suffers structural breakup ISRO seems to have made modifications to the GSLV for this flight, lengthening the rocket to carry extra fuel, and enlarging the faring to accommodate greater payload weight. The GSAT-5P communications satellite was the heaviest payload that ISRO has ever tried to launch. Either the modifications to the rocket resulted in new vibration modes that ISRO failed to account for, or else ground crew were simply careless during pre-launch checks, failing to ensure that all control cables were adequately secured. |
| Back to top |
|
|
Space Walker ![]()
Joined: Tue Sep 15, 2009 11:59 pm
Posts: 188 |
Let's look more closely at this:
http://netindian.in/news/2010/12/29/000 ... ro-sources Quote: "The take-off was smooth and the flight was normal till 47 seconds. But trouble arose in the next three seconds, when 10 connectors located between the second and third stage (cryogenic stage) got separated, leading to the vehicle losing controllability," the sources said. So that sounds like something could have happened with the cryogenic upper stage (CUS), that could have caused a major problem to the connectors below it. Could a cryo-propellant tank have ruptured/leaked due to aerodynamic stresses, and then disabled those connectors/cables? |
| Back to top |
|
|
Space Walker ![]()
Joined: Tue Sep 15, 2009 11:59 pm
Posts: 188 |
Flawed Shround Design Found to Cause GSLV Failure:
http://timesofindia.indiatimes.com/arti ... 032380.cms |